Week of 11/28/2018                                                Akash Sandhu

The guide arm design and assembly is complete. The mounted points have been added to both the drive and slave bogie guide arm. The last FEA was also completed for the slave bogie guide arm as show below. There are confirmed mounting points on the slave bogie. There still need to be mounting points made on the drive bogie. The goal is to finish up the report, and the bill of materials. The goal when the semester ends is to start working on Engineering drawings.
Factor of Safety = 3.321

Factor of Safety = 3.659